  • #511
    kathy
    Participant

      Dear all,

      recently, we discovered that some schedules were “Stopped”.
      The gray field on the left side of the schedule name displayed “Stopped”.
      Is there a way to figure out, if this was caused by a deployment or if these schedules were stopped manually?

      Thanks in advance, much appreciated.
      Best wishes,
      Kathy

      #533
      Lilian
      Participant

        Hi,

        if your account is using build version 5715 or higher, you can have a look at the Manage account > Info & Stats > User Transactions.
        Within the user transactions, you will be able to see if another user started or stopped a schedule.

        Best wishes,
        Lilian